Grey Structure Cost of a 5 Marla House (2026): Full Breakdown

Grey Structure Cost of a 5 Marla House (2026): Full Breakdown
A customer showed us two grey structure quotes for his 5 marla plot last month — they were miles apart. Neither was dishonest; one simply excluded the boundary wall, the septic chamber and half the plaster scope. Grey structure cost is only comparable when the scope is identical, so this guide fixes the scope first, then the quantities: what a 5 marla grey structure includes, the material quantities behind it for single and double story, and the questions to ask before you compare quotes.
What "grey structure" includes — and what it never includes
| Included in grey structure | Not included (finishing) |
|---|---|
| excavation and foundations | tile and marble flooring |
| RCC columns, beams, lintels | paint and wall finishes |
| RCC slabs, stairs and parapets | electrical wiring and fittings |
| brick masonry, all walls | plumbing fixtures and fittings |
| internal and external plaster | doors, windows and woodwork |
| mumty and water tank base | boundary wall (usually quoted separately) |
Everything above is the skeleton; everything below is what you see and touch. When comparing quotes, put this table in front of both contractors and ask exactly what each line costs.
The number the cost hangs on: covered area
A 5 marla plot measures 1,125 – 1,360 sq ft depending on the marla basis. Cost follows covered area, not plot size:
- Single story 5 marla: roughly 1,100 – 1,250 sq ft covered
- Double story 5 marla: roughly 2,000 – 2,400 sq ft covered (ground + first floor)
Material quantities behind a 5 marla grey structure
| Material | Single story | Double story |
|---|---|---|
| Bricks (awal) | 30,000 – 38,000 | 60,000 – 75,000 |
| Cement | 250 – 300 bags | 450 – 600 bags |
| Steel sariya | 1.5 – 2 ton | 3 – 4.5 ton |
| Sand (Chenab/Ravi) | 1,200 – 1,600 cft | 2,400 – 3,200 cft |
| Crush (Margalla/Sargodha) | 800 – 1,100 cft | 1,600 – 2,200 cft |
Cement is priced at the day's rate — see our cement rate guide before budgeting. The material-level detail lives in our brick counts for 5 marla houses and the construction material calculator guide.
The 2026 budget ranges
Across 2026, grey structure on a well-run site runs approximately:
- Materials (excluding cement): priced at the day's rate — call us with your covered area
- Labour: quoted per project — terms agreed at the time of contract
- Cement: at the day's rate — on these quantities it adds a meaningful separate line, not a rounding error
That puts a realistic 5 marla grey structure total at:
| House | Covered area | Grey structure total (est.) |
|---|---|---|
| Single story | about 1,150 sq ft | call us for the day's figure |
| Double story | about 2,200 sq ft | call us for the day's figure |
Treat these as ±10 – 15% bands: city, design, foundation depth and the year's material cycle all move them. The maths scales with the same logic as our 10 marla cost breakdown and the per-marla cost comparison; the Jhelum-specific version is in our grey structure cost guide for Jhelum.
Where 5 marla grey quotes blow up
- Scope shortcuts — no lintel schedule, "plaster where visible", stairs left unfinished. Every exclusion reappears as a finishing-stage bill.
- Thin slabs and wide spacing — the invisible saving that costs strength. Insist on the drawings.
- Cement by bag count, not by mix design — the bag count is an output of the design, not an input.
- Sariya by bundle guesswork — steel is paid by weighed weight; see our saria weight chart to check any bill.
- The forgotten line items — boundary wall, septic tank, water tank base, mumty, porch. List them explicitly.
Labour rate or with material?
We take grey structure work both ways around Jhelum: labour rate (you buy material, we build — best when you want control of purchasing) and with material (one quote, we supply and build — best when you want one throat to choke on quality). The trade-offs are the same for porches and room additions — see how we price those in the lanter and porch roof guide and the builders guide.
Frequently asked
What is included in the grey structure of a 5 marla house? Foundations, RCC structure (columns, beams, slabs, stairs), brick walls, internal and external plaster, parapets and mumty — not flooring, paint, wiring fixtures, plumbing fittings or woodwork.
How many cement bags for 5 marla double story grey structure? Typically 450 – 600 bags depending on slab spans and wall quantities. Your drawings decide the exact number; our Cement Calculator gives a close estimate in a minute.
Is grey structure cheaper on labour rate or with material? The totals land within a few percent either way on an honest job. Labour rate suits buyers who want to purchase material themselves; with-material suits those who want one responsible party. What actually moves the price is the scope table — get that fixed first.
Build the grey once, build it right
Grey structure is the part of the house you never see again after plaster — and the part you can never fix cheaply. Send your plan or plot details on WhatsApp to +92 331 5083 648 or request a quote, and we will return a line-by-line grey scope you can compare against any other quote. Use our Grey Structure Calculator to size the materials before you talk numbers.
Ordering & Rates — Confirmed on Call
Material rates change daily, so we confirm everything directly with you.
Today's rate, not yesterday's: Cement, steel, bricks, sand, crush and paint rates move with the market, sometimes daily. Call or WhatsApp +92 331 5083 648 and our team confirms the day's exact figure for your brand and quantity in minutes.
Straight, itemised quotes: Tell us your material list — a paper chit, a photo of your plan or just your plot size and stage. You get brand, grade and quantity spelled out, and the figure is locked only with an official order and advance payment.
Everything confirmed personally: Availability, quantities, timing and how the material reaches you — we confirm all of it with you directly before anything is finalised. No surprises at loading.
Full details in our Contact page — or call / WhatsApp +92 331 5083 648 and we will go through your list and today's rate in minutes.
Good to Know Before You Act
Two honest notes about everything published in our guides.
We don't publish fixed rates: material rates in Pakistan change daily, so nothing on this site is a price list. The final and correct rate is always the one our team confirms with you on the day. Call or WhatsApp +92 331 5083 648 for today's exact figure — a rate is locked only with an official order and advance payment.
Guidance, not instructions: quantities, mix ratios and methods described in our guides are general educational guidance for your specific site you should verify — outcomes depend on site conditions, water quality, handling, curing, storage and workmanship. Before you act, always speak with your engineer, contractor or a qualified professional — or ask our team for guidance on materials.
Planning a stage of your project? Contact us first — we will gladly go through your material list, today's rate and the right products for your site before you buy.
Related Articles
Lanter (Lintel) Beams and Porch Roofs: Cement, Saria and Cracks You Can Avoid
A crack two winters old, right above a door. Nine times out of ten the lanter is the story — here is how lintels and porch roofs are done around Jhelum.
Best Month to Start House Construction in Pakistan — A Jhelum Answer
There is no magic month, but there are smart ones. How monsoon, winter and peak season change foundations, curing, mistri availability and material rates — and the two windows local builders actually aim for.
10 Marla House Construction Cost in Pakistan (2026) — Full Breakdown
What a 10 marla house really costs in 2026: grey structure quantities (bricks, cement, steel, sand, crush), labour rates, finishing costs and realistic total budgets from economy to premium.