5 Marla House Construction Cost in Jhelum: Complete Breakdown

Khokhar TradersJuly 1, 202611 min read
5 Marla House Construction Cost in Jhelum: Complete Breakdown

If you're planning to build a 5 marla house in Jhelum, the first thing you need is a realistic budget. Not a rough estimate someone gave you on WhatsApp — an actual item-by-item breakdown so you know exactly where every rupee goes.

I've helped dozens of families in Jhelum plan their 5 marla house construction through Khokhar Building Material Supplier. This guide gives you the real numbers for 2026 — not inflated contractor quotes, not impossibly low estimates, but what it actually costs to build a quality house in Jhelum today.

Understanding 5 Marla Plot Dimensions

First, let's clarify what a 5 marla plot actually is:

  • Plot area: 5 marla = 1,125 sq ft (25 ft × 45 ft typical)
  • Covered area (double story): 1,800 - 2,200 sq ft
  • Ground floor covered: 900 - 1,100 sq ft
  • First floor covered: 900 - 1,100 sq ft

Covered area is always less than plot area because you need space for:

  • Setbacks (front and rear open spaces)
  • Staircase area
  • Courtyard or open space

For our calculations, we'll use 2,000 sq ft total covered area for a double-story 5 marla house — a typical figure for standard construction in Jhelum.

Construction Quality Tiers

Before we break down costs, understand the three quality levels:

TierRate per Sq FtTotal Cost (2,000 sq ft)What You Get
Grey Structurecall usthe day's rate — call usStructure only, no finishes
A-Classcall usthe day's rate — call usQuality finishes, livable
Premiumcall usthe day's rate — call usHigh-end finishes, luxury

For a deeper explanation of these tiers, read our construction rate per square foot guide.

Grey Structure Cost Breakdown

Let's start with the grey structure — the foundation, walls, and roof without any finishing work.

1. Foundation and Excavation

ItemQuantityRate (PKR)Total (PKR)
Excavation1,500 cft15/cft22,500
Hardcore filling (brick bat)300 cft30/cft9,000
PCC (1:4:8)100 cft—15,000
Foundation concrete (1:2:4)150 cft—65,000
Foundation brickwork15,000 bricks24/piece360,000
DPC (damp proof course)500 sq ft35/sq ft17,500
Subtotal489,000

2. Main Structure (Walls and Slabs)

ItemQuantityRate (PKR)Total (PKR)
Bricks (superstructure)50,00024/piece1,200,000
Cement (OPC 53 — Cherat / Fecto / Flying Pakistan)350 bagstoday's ratecall us
Sand (Channan)600 cft45/cft27,000
Crush (Bajri)450 cft110/cft49,500
Steel (Grade 60)6,500 kg300/kg1,950,000
RCC slab (ground floor)1,000 sq ft—600,000
RCC slab (first floor)1,000 sq ft—650,000
Columns and beams——180,000
Subtotalcall for today's rate

3. Plaster (Internal and External)

ItemQuantityRate (PKR)Total (PKR)
Internal plaster (cement-sand)4,500 sq ft25/sq ft112,500
External plaster2,500 sq ft28/sq ft70,000
Ceiling plaster2,000 sq ft22/sq ft44,000
Subtotal226,500

4. Labor and Supervision

ItemTotal (PKR)
Masonry labor (per 1,000 bricks)350,000
Slab pouring labor120,000
Plaster labor200,000
Helper/Mazdoor150,000
Supervision/Engineer100,000
Subtotal920,000

5. Other Grey Structure Items

ItemTotal (PKR)
Underground water tank (1,000 gallon)80,000
Septic tank40,000
Basic plumbing (pipes only)120,000
Basic electrical (conduits only)80,000
Roof waterproofing55,000
Scaffolding and shuttering45,000
Misc and contingency100,000
Subtotal520,000

Grey Structure Grand Total

CategoryCost (PKR)
Foundation489,000
Main structurecall for today's rate
Plaster226,500
Labor920,000
Other items520,000
Total Grey Structure~7,288,000

For 2,000 sq ft, that works out to approximately the day's rate — call us per sq ft — right in the grey structure range.

Finishing Cost Breakdown (A-Class)

Now let's add finishing to make the house livable at A-class quality.

1. Flooring

AreaSq FtMaterialRate/sq ftTotal (PKR)
Ground floor tiles1,000Porcelain 24x24200200,000
First floor tiles1,000Porcelain 24x24200200,000
Staircase tiles120Anti-skid25030,000
Kitchen counter40Granite80032,000
Bathroom walls (dado)400Ceramic18072,000
Tile installation labor2,560—40102,400
Subtotal636,400

2. Doors and Windows

ItemQuantityRate (PKR)Total (PKR)
Main door (solid wood)125,00025,000
Internal doors (flush)78,00056,000
Bathroom doors (PVC/waterproof)36,00018,000
Door hardware (locks, hinges)——30,000
Aluminum windows812,00096,000
Window grills85,00040,000
Subtotal265,000

3. Electrical Work

ItemQuantityRate (PKR)Total (PKR)
Wiring (complete house)——150,000
Switches and sockets (BRK/Leo)6050030,000
Distribution board + MCBs28,00016,000
Ceiling fans84,50036,000
LED lights and fixtures301,50045,000
Exhaust fans33,50010,500
Subtotal287,500

4. Plumbing

ItemQuantityRate (PKR)Total (PKR)
Bathroom fittings (3 baths)3 sets35,000105,000
Kitchen sink and fittings1 set15,00015,000
Water motor and tank120,00020,000
Geyser connections33,0009,000
Pipes and fittings——45,000
Subtotal194,000

5. Paint and Finishing

ItemQuantityRate (PKR)Total (PKR)
Primer15 liters2503,750
Interior emulsion50 liters35017,500
Exterior weather shield30 liters55016,500
Enamel (doors/windows)10 liters5005,000
POP cornice and ceiling2,000 sq ft3060,000
Painter labor——60,000
Subtotal162,750

6. Kitchen and Woodwork

ItemTotal (PKR)
Kitchen cabinets (lower + upper)150,000
Wardrobes (3 bedrooms)180,000
Bathroom vanities30,000
Subtotal360,000

7. Miscellaneous

ItemTotal (PKR)
Main gate (iron)45,000
Staircase railing35,000
Boundary wall gate15,000
Grill work (windows)Already included
Exterior elevation work80,000
Contingency (5%)100,000
Subtotal275,000

Finishing Grand Total

CategoryCost (PKR)
Flooring636,400
Doors and windows265,000
Electrical287,500
Plumbing194,000
Paint and finishing162,750
Kitchen and woodwork360,000
Miscellaneous275,000
Total Finishing~2,180,650

Total Construction Cost Summary

PhaseCost (PKR)Per Sq Ft
Grey structure7,288,0003,644
Finishing (A-Class)2,180,6501,090
Total A-Class Construction~9,468,650~4,734

This comes to approximately the day's rate — call us per sq ft — which is actually on the lower end of A-class because we've used mid-range materials throughout. If you upgrade to premium tiles, imported fittings, and solid wood doors, expect to add the day's rate — call us per sq ft.

Additional Costs Most People Forget

Beyond the construction itself, budget for these:

ItemCost (PKR)
House map/design approval30,000 - 80,000
BCA/JDA approval fees50,000 - 100,000
Electricity connection (new)50,000 - 80,000
Gas connection30,000 - 60,000
Water connection10,000 - 20,000
Boundary wall (complete)200,000 - 300,000
Driveway and entrance80,000 - 150,000
Landscaping (basic)50,000 - 100,000
Total additional500,000 - 890,000

Grand Total for a Move-In Ready 5 Marla House

CategoryCost Range (PKR)
Grey structurethe day's rate — call us
Finishing (A-Class)the day's rate — call us
Additional coststhe day's rate — call us
Totalthe day's rate — call us

So for a quality 5 marla double-story house in Jhelum, budget approximately the day's rate — call us including everything.

How to Reduce Cost Without Compromising Quality

  1. Use A-grade bricks instead of A+ premium for non-visible walls — saves the day's rate — call us+ on a 5 marla house. Check current brick rates.

  2. Choose mid-range tile brands — local brands like Sonite, Shabbir Tiles, and Master Tiles offer good quality at 30-40% less than imported tiles. See our tiles selection guide.

  3. Use OPC 53 grade for structure, masonry and plaster alike — it is the grade our local market builds with. Ask us and we'll quote today's rate. Read our cement brands comparison.

  4. Do woodwork after moving in — wardrobes and kitchen cabinets can be added gradually as budget allows.

  5. Phase your finishing — do essential finishing first (flooring, doors, basic paint), upgrade other items later.

  6. Buy materials yourself — contractors typically add 10-15% markup on materials. Buying directly from Khokhar Building Material Supplier saves this margin.

Where You Should NOT Cut Costs

  • Foundation and structural steel — never compromise here
  • RCC slab — use proper steel grades and cement. See our RCC slab guide
  • Waterproofing — roof and bathroom waterproofing is critical
  • Electrical wiring — cheap wiring is a fire hazard
  • Plumbing pipes — hidden inside walls, very expensive to replace later

Construction Timeline and Payment Schedule

For a 5 marla house, here's a typical timeline and when you'll need money:

MonthPhasePayment Due (PKR)
Month 1Excavation and foundationthe day's rate — call us
Month 2-3Brickwork (ground floor)the day's rate — call us
Month 4Ground floor slabthe day's rate — call us
Month 5-6Brickwork (first floor) + slabthe day's rate — call us
Month 7Plasterthe day's rate — call us
Month 8-9Flooring, doors, windowsthe day's rate — call us
Month 10-11Electrical, plumbing, paintthe day's rate — call us
Month 12Woodwork, finishing, handoverthe day's rate — call us
Total~the day's rate — call us

Spread over 12 months, that's roughly the day's rate — call us per month — plan your cash flow accordingly.

Final Advice

Building a 5 marla house is a major project. The numbers in this guide are realistic for 2026 construction in Jhelum — not the lowest possible, not the highest, but what quality construction actually costs.

Work with a reliable builder (check our guide to choosing builders), source materials from a trusted supplier, and keep a 10% contingency fund for unexpected costs. Visit your site regularly — no contractor does their best work when the owner is absent.

At Khokhar Building Material Supplier, we help homeowners plan their material purchases to match their construction timeline and budget. Bring your house plan, and we'll work out a material schedule that keeps your project moving without overcommitting your cash at any one time.

Build it right, build it once. A house constructed properly today will serve your family for decades without the headache of constant repairs and renovations. ===END===

A Real 5 Marla Sequence, Step by Step

Per-marla tables are useful, but a real build is a sequence of decisions. Here is how a typical 5 marla house in areas like Bilal Town or Kala Gujran actually unfolds from the supplier's seat:

  • Paperwork and covered area first. Marla maths varies (our marla-to-square-feet converter helps), and the covered area — not the plot — drives material quantities. Get the drawing stamped before the first trolley.
  • Foundation stage. Excavation depth follows your soil. Materials here are bricks, OPC 53 grade cement, sand, crush and Grade 60 steel per drawings. The decisions made this week are the ones you cannot revisit later.
  • Masonry and columns. Bricks by stage, cement brand consistent, and the first real risk appears: weather. Jhelum's winter fog slows curing badly and monsoon weeks can flood an open pit — stage your orders around the forecast, not the calendar.
  • The slab pour. One day, one brand, one grade, enough hands. Most delays we see are slab-day logistics: a truck that could not enter the street, a mixer that arrived late, water pressure that failed at noon. Plan the pour for the morning and read our slab-logistics notes before the day.
  • Plaster and waiting. Good plaster is rushed nowhere: sand quality, curing days, and patience between coats.
  • Finishing last — deliberately. Tiles, paint tiers, woodwork: choose these when the structure is standing, with a margin kept flexible on purpose.

The totals in the table above are estimates — material rates move daily. For a line-item picture of your actual covered area, use the calculators and send your drawing for an itemised quotation.

Questions about your own build? Call or WhatsApp +92 331 5083 648 — we answer with today's facts, not guesses.

Ordering & Rates — Confirmed on Call

Material rates change daily, so we confirm everything directly with you.

  • Today's rate, not yesterday's: Cement, steel, bricks, sand, crush and paint rates move with the market, sometimes daily. Call or WhatsApp +92 331 5083 648 and our team confirms the day's exact figure for your brand and quantity in minutes.

  • Straight, itemised quotes: Tell us your material list — a paper chit, a photo of your plan or just your plot size and stage. You get brand, grade and quantity spelled out, and the figure is locked only with an official order and advance payment.

  • Everything confirmed personally: Availability, quantities, timing and how the material reaches you — we confirm all of it with you directly before anything is finalised. No surprises at loading.

Full details in our Contact page — or call / WhatsApp +92 331 5083 648 and we will go through your list and today's rate in minutes.

Good to Know Before You Act

Two honest notes about everything published in our guides.

  • We don't publish fixed rates: material rates in Pakistan change daily, so nothing on this site is a price list. The final and correct rate is always the one our team confirms with you on the day. Call or WhatsApp +92 331 5083 648 for today's exact figure — a rate is locked only with an official order and advance payment.

  • Guidance, not instructions: quantities, mix ratios and methods described in our guides are general educational guidance for your specific site you should verify — outcomes depend on site conditions, water quality, handling, curing, storage and workmanship. Before you act, always speak with your engineer, contractor or a qualified professional — or ask our team for guidance on materials.